Intelligent Investment
Austin-San Antonio
North America Data Center Trends H1 2025
września 8, 2025 4 Czas spedzony na stronie Read
Colocation Insights
- The overall vacancy rate remained near a record low at 2.3%.
- Pricing remained steady over the first half of the year.
- Under-construction capacity is 97% preleased.
Market Trends
- Hyperscalers and AI providers continued to show an interest in the market.
- Developers are focused on the northeast suburbs of Austin for available land served by Oncor.
- Increased interest in the Austin area has pushed activity south of Austin in Lower Colorado River Authority territory.
Notable Activity
- Under-construction activity totaled 462.0 MW.
- Three operators completed construction on fully preleased facilities.
- Regional utility providers are receiving historically large power requests.
Figure 1: Historical Market Information
Figure 2: Historical Supply and Demand
Figure 3: % of Total Secondary Market Inventory
Figure 4: Market Fuel Mix
Figure 5: Average Asking Rates
Explore More Markets
- LocalResponse | Intelligent Investment
Atlanta Data Center Market
września 8, 2025 4 Czas spedzony na stronie Read
Metro Atlanta data center market faces challenges, but new projects can be completed by 2027 with strong demand and planning.
- LocalResponse | Intelligent Investment
Dallas-Ft. Worth Data Center Market
września 8, 2025 4 Czas spedzony na stronie Read
Dallas-Ft. Worth data center market to double in size by 2026 with 89% of under-construction space preleased.
- LocalResponse | Intelligent Investment
Houston Data Center Market
września 8, 2025 4 Czas spedzony na stronie Read
Market vacancy reaches 19.7% as 15MW of new capacity is scheduled for delivery by 2026, driven by oil and gas demand.
Data Center Solutions
Report Contacts
Brant Bernet
Executive Vice President